Looking for 2 PMP certified professionals with a great command in English to prepare questions for PMP Prep.

Job Details and Discussion points
1. Creation of questions are not done from scratch as the questions are already selected from various paid and free sources
2. The selected questions need to be reworded and edited to ensure copyrights are not infringed
3. The type of questions don’t need to be changed but they need to be repositioned to look and sound different
4. Each question also comes with explanation that also need to be edited
5. I have attached an example of original vs. re-worded question for your reference
6. You will be paid 20 cents for each question. There are over 1000 questions that need to be edited and the more you can edit the more you make
7. I will be providing you the original question and you will need to edit them and send it back

Original Question and Explanation
Q1 What among the following would be the appropriate stage for establishing resource requirements on the project?
A. After schedule development is completed
B. After creating project network diagram
C. After scope statement
D. Before activity definition
Answer B
Resource requirements are required to estimate activity duration and follow the creation of the schedule network diagram. Schedule development can be completed only after establishing resource requirements. Resource requirements do not have impact on scope statement and activity definition.

Re-worded Question and Explanation
Q1 You are managing a large global project that is suffering from resource commitments from different parts of the organization. You are in the planning stages, what will be the appropriate time for establishing resource requirements on your project?
A. As soon as the scope statement is completed
B. Before the activity definition phase of the project
C. After you have completed the project schedule
D. Right after creating the project network diagram
Answer D
Resource requirements are key to estimate the activity duration and can only be completed after the schedule network diagram has been prepared. Option C on schedule development can only be completed after you have establishing the resource requirements. There is no impact of resource requirements on scope statement and activity definition.

---
Skills: english